WORKS UNDER PWD (NH), NAGALAND.
1. Under NH (O) Works
Sl No. |
Name of Work/Project |
Length (Km) |
Sanctioned Cost (Rs. in Crore) |
Date of Sanction |
1 |
Widening of existing single/intermediate lane road to 2 lane road from km. 72.4.to km 83.00 on NH-61 in the state of Nagaland on EPC mode |
10.44 |
122.31 |
09.01.2020 |
2 |
Widening of existing Single lane / Intermediate lane road to 2 lane from Km 101 to Km 125 of NH 61 in the state of Nagaland |
24.00 |
252.19
|
23.06.2020 |
3 |
Development of Existing 2 Lane pavement including strengthening of NH-36 from Km160/000 to Km 166/880 in Dimapur City Portion in the State of Nagaland. |
6.88 |
22.12 |
02.02.2021 |
4 |
Widening of Existing Single lane road to intermediate lane road from Mokokchung to Chare via Dikhu in the state of Nagaland |
20.64 |
192.93 |
19.02.2021 |
5 |
Widening to Existing single lane /intermediate lane to 2 lane from Km185.00 to Km 220.00 of NH-61 (New NH-02) in the state of Nagaland. |
31.05 |
297.24 |
31.03.2021 |
6 |
Widening to Existing single/intermediate lane to 2 lane from Km 135 to Km 147 and from Km 156.00 to Km 168.00 of NH-61 (new NH-2) in the state of Nagaland |
23.06 |
226.44 |
31.03.2021 |
7 |
Strengthening of road from km 6.00 to km 40.00 of NH-61 (new NH-2) under NH division Kohima in the state of Nagaland for the year 2021-22 |
34.00 |
58.92 |
03.01.2022 |
8 |
Rehabilitation of Dimapur RoB at Km 108.240 on NH-29 in the State of Nagaland under Annual Plan 2022-23 |
– |
2.79 |
28.03.2023 |
2. Under Short Term Maintenance (STMC) Works:
Sl No. |
Name of Work/Project |
Length (Km) |
Sanctioned Cost (Rs. in Crore) |
Date of Sanction |
1 |
Short Term Maintenance Contract to NH-202 (Old-155) from Km 177.00 to Km 190.00 & Km 241.00 to Km 283.00 under NH Division Kiphire in the state of Nagaland. |
55.00 |
4.01 |
24.01.2023 |
2 |
Short Term Maintenance Contract to NH-02 (Old-61) from Km 101.00 to Km 125.00 Km under NH Division Mokokchung in the state of Nagaland. |
24.00 |
2.73 |
24.01.2023 |
3 |
Short Term Maintenance Contract to NH-702D from Km 0.00 to Km 63.00 under NH Division-II, Mokokchung in the state of Nagaland. |
63.00 |
4.99 |
24.01.2023 |
4 |
Short term maintenance contract to NH-702A from Km 153.000 to Km 173.000 (Total length= 45.00 Km) under PWD(NH), Division-VI, Phek in the State of Nagaland. |
20.00 |
2.14 |
24.01.2023 |
5 |
Short term maintenance contract to NH-702A from Km 176.000 to Km 221.000 (Total length= 45.00 Km) under PWD(NH), Division-VI, Phek in the State of Nagaland |
45.00 |
3.00 |
24.01.2023 |
6 |
Short term maintenance contract to NH-202 (Old-155) from Km 39.00 to Km 120.00 under NH Division Tuensang in the state of Nagaland |
81.00 |
4.99 |
24.01.2023 |
7 |
Short Term Maintenance Contract to NH-202 ( NH-155 ) from Km 130.00 to km 140.00 and km 145.00 to km 177.00 under NH Division Tuensang in the State of Nagaland. |
42.00 |
4.96 |
24.01.2023 |
8 |
Short term maintenance contract to NH-202 (Old-155) from Km 0.00 to Km 39.00 Km under NH Division Tuensang in the state of Nagaland. |
39.00 |
4.96 |
24.01.2023 |
9 |
Short Term Maintenance Contract to NH-202 (NH-155) for Km 154.300 to Km 154.380 under NH Division Tuensang in the State of Nagaland. |
0.08 |
1.17 |
24.01.2023 |
3. Under Project Management Consultancy Services (PMC) Works
Sl No. |
Name of Work/Project |
Length (Km) |
Sanctioned Cost (Rs. in Crore) |
Date of Sanction |
1 |
Project Management Consultancy Services for Preparation Of Detailed Project Report, Pre-construction activity and construction supervision of 2-Laning with paved shoulder from Mokukchung to Zunheboto, Chozuba to phek and from Losami junction to Meluri (Length=143.00 Km) on NH-702A in the state of Nagaland |
143.00 |
24.76 |
09.03.2023 |
2 |
Project Management Consultancy Services for preparation of detailed Project report, pre-construction activity and construction supervision of 2-laning with paved shoulder from Mokokchung to Watiyim (Length=70.00 Km) on NH-702D in the State of Nagaland |
70.00 |
15.35 |
27.03.2023 |
4. Under IRQP/PR Works
Sl No. |
Name of Work/Project |
Length (Km) |
Sanctioned Cost (Rs. in Crore) |
Date of Sanction |
1 |
Improvement of Riding Quality (IRQP) on NH 702A from km 16.00 – 35.00 km and km 40.00 – 53.00 km under NH Div-II Mokokchung in the State of Nagaland (Length=32.00Km) under Annual Renewal Plan 2022-23 |
32.00 |
16.17 |
21.02.2023 |