Projects under National Highways

1.      UNDER NH(O)-
(i) STRENGTHENING,CONSTRUCTION & IMPROVEMENT OF ROADS /CONSTRUCTION & REHABILITATION OF BRIDGES-
Sl No Particulars Sanction Amount (rs in cr) NH No Length Status (Physical Progress in %)
(Km)/No
1 Reconstruction of Major Bridge over River Doyang on NH-61 at Km 105/00 under NH Division Kohima in the State of Nagaland 14.37 02 1 92.00%
2 Strengthening and widening to two lane with paved shoulder of NH-61 from Km 40.00 to Km 72.40 under EPC mode in the state of Nagaland during 2016-17 (Package-I from Km 40.00 to Km 56.00) 167.62 02 16 20.27%
3 Strengthening and widening to two lane with paved shoulder of NH-61 from Km 40.00 to Km 72.40 under EPC mode in the state of Nagaland during 2016-17 (Package-II from Km 56.00 to K 72.40) 172.63 02 16.4 29.11%
4 Improvement of city portion of kohima and dimapur city of NH-39 in the State of Nagaland under EPC mode during 2016-17 ( Packagae -I dimapur city from Km 106.90 to 124.20) 369.96 29 & 129 17.3 10.24%
5 Improvement of city portion of kohima and dimapur city of NH-39 in the State of Nagaland under EPC mode during 2016-17  (Package-II Kohima City from Km 177.60 to Km 187.60) 139.11 29 & 02 10 74.88%
6 Construction of 2 lane with paved shoulder from Km. 168 to 183.783 (Yesemyong to Unger) on Mokokchung  to Tuli Section of NH-61 under EPC mode in the State of Nagaland. 217.35 02 17 129%
TOTAL 1081.04 76.7
(ii) FEASIBILITY STUDY/DETAILED ENGINEERING:
Sl No Particulars Sanction Amount (rs in cr) NH No Length Status
(Km)
1 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Longleng-Longching-Mon-Tizit-Namtola of NH-702 6.05 702 143 Under Tendering
2 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Aboi to Tuensang 4.41 702B 104 Under Tendering
3 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder (Mokokchung- Mariani) 3.32 702D 78.5 Under Tendering
4 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Pimla-Junction, Diphu on NH 329, sub jail junction on NH 36 to NH 129A via Thahekhu and Chumudedima to Dimapur bypass 2.08 329A & 229 49 Under Tendering
5 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Showuba-Guzunyu-Pughoboto- Zunheboto-Aghunato-Noklak-Pangsha 8.47 In Principle Approved NH 200 Under Tendering
6 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Trans Eastern Highway from Mon-Longwa-Pangsha-Kiphire-Avangkhu 11.86 In Principle Approved NH 280 Under Tendering
7 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Mokokchung-Zunheboto & Chazuba to Meluri via Thevopheshu on NH-702A under NH(O) 14.05 702A 226 Under Tendering
8 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder from NH-29 to NH-29 (new NH Nos.) Dimapur Bypass 0.17 In Principle Approved NH 2.7 Under Tendering
9 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Gandhi Ashram Chuchuyimlang (NH-2) to Pangsha   (International Trade Centre) 10.38 In Principle Approved NH 167 Under Tendering
10 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Maibung in Tening in Nagaland to Tamenlong via Tamei in Manipur 4.67 In Principle Approved NH 75 Under Tendering
11 Consultancy services for Feasibility Study and Detailed Project Report for two-laning with paved shoulders of Athibung-Khelma (Phase-B of SARDP-NE) 2.32 SARDP 55 Under Tendering
12 Consultancy services for project management incharge of foothill road from Amguri NH-61 to Niiuland via Longchem-Changpang-Governor’s Camp (Phase-B of SARDP-NE) 8 SARDP 189 Under Tendering
TOTAL 75.78 1569.2
(ii) FEASIBILITY STUDY/DETAILED ENGINEERING:
(a) On Existing NH
Sl No Particulars Sanction Amount (rs in cr) NH No Length Status
(Km)
1 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Longleng-Longching-Mon-Tizit-Namtola of NH-702 6.05 702 143 Approval of Draft DPR awaited
2 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Aboi to Tuensang 4.41 702B 104 Under Tendering
3 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder (Mokokchung- Mariani) 3.32 702D 78.5 Under Tendering
4 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Pimla-Junction, Diphu on NH 329, sub jail junction on NH 36 to NH 129A via Thahekhu and Chumudedima to Dimapur bypass 2.08 329A & 229 49 Under Tendering
5 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Mokokchung-Zunheboto & Chazuba to Meluri via Thevopheshu on NH-702A under NH(O) 14.05 702A 226 Under Tendering
TOTAL 29.91 600.5
(b) In-Principle” approved NH
Sl No Particulars Sanction Amount (rs in cr) NH No Length Status
(Km)
1 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Showuba-Guzunyu-Pughoboto- Zunheboto-Aghunato-Noklak-Pangsha 8.47 In Principle Approved NH 200 Under Tendering
2 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Trans Eastern Highway from Mon-Longwa-Pangsha-Kiphire-Avangkhu 11.86 In Principle Approved NH 280 Under Tendering
3 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder from NH-29 to NH-29 (new NH Nos.) Dimapur Bypass 0.17 In Principle Approved NH 2.7 Under Tendering
4 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Gandhi Ashram Chuchuyimlang (NH-2) to Pangsha   (International Trade Centre) 10.38 In Principle Approved NH 167 Under Tendering
5 Consultancy services for preparation of Feasibility Study and Detailed Project Report for 2-laning with paved shoulder of Maibung in Tening in Nagaland to Tamenlong via Tamei in Manipur 4.67 In Principle Approved NH 75 Under Tendering
TOTAL 35.55 724.7
2. UNDER SARDP-NE
Sl No Particulars Sanction Amount (rs in cr) NH No Length Status
(Km)
1 Consultancy services for Feasibility Study and Detailed Project Report for two-laning with paved shoulders of Athibung-Khelma (Phase-B of SARDP-NE) 2.32 SARDP 55 Under Tendering
2 Consultancy services for project management incharge of foothill road from Amguri NH-61 to Niiuland via Longchem-Changpang-Governor’s Camp (Phase-B of SARDP-NE) 8 SARDP 189 Approval of Final DPR awaited
TOTAL 10.32 244
3. UNDER ANNUAL RENEWAL PROGRAM
Sl No Particulars Sanction Amount (rs in cr) NH No Length Status
(Km)
1 IRQP work from Km 130.00 to Km 140.00 on NH-202 (Old NH-155) under NH Division-III, Tuensang in the State of Nagaland. 4.75 202 10 Works Awarded on 17.01.2019
2 PR from Km 272.00 to Km 284.00 on NH-202 (Old NH-155) under NH Division-IV, Kiphire in the State of Nagaland. 6 202 12 Under Tendering
3 PR from km 131.00 to km 141.00 on NH-702 under NH Division, Mon in the State of Nagaland. 5.17 702 10 Works Awarded on 17.01.2019
4 PR from km 155.00 to km 160.00 on NH-702 under NH Division, Mon in the State of Nagaland. 2.48 702 5 Works Awarded on 17.01.2019
5 PR from Km 16.00 to Km 25.00 on NH-702A under NH Division-II, Mokokchung in the State of Nagaland. 4.45 702A 9 Works Awarded on 17.01.2019
6 PR from Km 25.00 to Km 35.00 on NH-702A under NH Division-II, Mokokchung in the State of Nagaland. 4.7 702A 10 Works Awarded on 17.01.2019
7 PR from Km 25.00 to Km 30.00 on NH-702D under NH Division-II, Mokokchung in the State of Nagaland. 2.41 702D 5 Works Awarded on 17.01.2019

 

 

Under NH(O)-Road Works
Sl. No Name of the Project Length (in Km) NH No & Project Stretch Sanction Civil Amount/Work order Amount (Rs. in Crores) Status
1 Improvement of Sharp curves on various locations and improvement of drainage with RCC cover slab within Kohima Town from Km 0.00 to km 6.00 on NH-61 under NH Division No.1 Kohima 6 NH-02

Kohima (TCP Gate)-I.G Stadium

6.12 Ongoing
2 Strengthening and widening to two lane with paved shoulder of NH-61 from Km 40.00 to Km 72.40 under EPC mode (Package I from Km 40.00 to Km 56.00) 16 NH-02

Botsa- New Tesophenyu

118.00 LOA issued
3 Strengthening and widening to two lane with paved shoulder of NH-61 from Km 40.00 to Km 72.40 under EPC mode (Package II from Km 56.00 to Km 72.40) 16.4 NH-02

New Tesophenyu-Longsa Gate (near Wokha)

125.66 LOA issued
4 Improvement of city portion of kohima City ( Km 177.60 to Km 187.60) and dimapur city ( Km 106.90 to Km 124.20) of NH-39  (Package -I dimapur city Km 106.90 to Km 124.20) 17.3 NH-129 & NH-29

New field Check Gate-Tragopan Hotel Jn.-Patkai bridge

279.39 LOA issued
5 Improvement of city portion of kohima City ( Km 177.60 to Km 187.60) and dimapur city ( Km 106.90 to Km 124.20) of NH-39 (Package -II kohima city Km 177.60 to Km 187.60) 10 NH-29 & NH-02

Municipal Gate Kohima-Phesama Police Check Gate

111.11 LOA issued
6 Strengthening of existing pavement and providing paved shoulder from Km 125 to Km 135 on NH-2 10 NH-02

Izheto (near VK) – Alichen

16.78 LOA issued
7 Construction of 2 lane with paved shoulder from  Km. 168 to 183.783 (Yesemyong to Unger) on Mokokchung  to Tuli Section of NH-61 under EPC mode 15.78 NH-02 Yesemyong-

Unger

217.35 Under Tendering

 

Under NH(O)-Bridge Works
Sl. No Name of the Project Length (in Km) NH No. Sanction Civil Amount/Work order Amount (Rs. in Crores) Status
1 Construction of composite Bridge over river Tsusangra at Km 219.500 (Design Km 210.120) on NH-61 under NH Mokokchung Division NA NH-02 12.59 Ongoing
2 Reconstruction of Major Bridge over River Doyang on NH-61 at Km 105/00 under NH Division Kohima NA NH-02 6.09 Ongoing
3 Repair and rehabilitation of Doyang Bridge (NH-2) and Dhansiri Bridge (NH-29) under NH Division Kohima NA NH-02 & NH-29 1.11 Ongoing
4 Repair and rehabilitation of existing 3 (three) Nos. of Steel Bridges on NH-202 (NH-155 old) from km 177.00 to Km 326.00 NA NH-202 3.64 Ongoing

 

Under PR/IRQP
Sl. No Name of the Project Length (in Km) NH No Sanction Civil Amount/Work order Amount (Rs. in Crores) Status
1 IRQP  to NH – 202 from 60.00km to 66.00km in the state of Nagaland under NH Division-III,  Tuensang 6 NH-202 2.11 Ongoing
2 IRQP on NH-202 from km 66.00 to km 72.00 under NH Tuensang Division 6 NH-202 2.00 Ongoing
3 IRQP to NH – 202 from 107.00km to 120.00km under NH Division-III,  Tuensang 13 NH-202 5.03 Ongoing
4 IRQP to NH – 202 from 177.00 km to 190.00 km under NH Division Kiphire 13 NH-202 5.94 Ongoing
5 IRQP to NH – 202 from 230.000 km to 231.000 km and 248.000 km to 252.000 km under NH Division Kiphire 5 NH-202 2.27 Ongoing
6 IRQP on NH 702A from km 5.46 to km 16.00 under NH Mokokchung Division 10.54 NH-7020A 3.96 Ongoing
7 IRQP on NH702A from km 40.00 to km 53.00 under NH Mokokchung Division 13 NH-7020A 5.36 Ongoing
8 IRQP on NH 702D from km 0.00 to km 10.00 under NH Mokokchung Division 10 NH-702D 3.72 Ongoing
9 IRQP on NH 702D from km 10.00 to km 25.00 under NH Mokokchung Division 15 NH-702D 3.84 Ongoing
10 IRQP of NH702D from km 30.00 to km 50.00 under NH Mokokchung Division 20 NH-702D 6.47 Ongoing